This project consisted of and industrial cement distribution terminal and site work. The schedule was of prime importance. Weather delays were overcome and the schedule was preserved. However, during start-up and initial operation of the plant after completion, it was discovered that some of the equipment did not meet the requirements necessary to proper operations. The Renaissance Companies took immediate steps to work with the owner to solve these issues. This was particularly challenging since the party responsible for the plant design was not available to us, because of financial constraints.

The State of the Art facility was a challenge to build. As a team, we stepped in and corrected the design deficiencies and making the necessary changes, all while the plant was in operation. The Renaissance companies team members worked around the clock replacing valves, correcting program deficiencies and completing other steps to bring the plant up to full design capability. Teamwork and dedication to satisfying the client made this project a success.