The project consisted of a 230,000 SF concrete-over-steel deck mezzanine and a build-out of a 40,000 SF LEED Silver tenant improvement. The Renaissance Companies also installed two service entrance sections, re-configured the lighting and placed/energized over 240 packaged air conditioning units on the roof by helicopter. The project was completed in 13-weeks by working 2-10 hour shifts a day, six days a week and with a crew of over 500 people. The Architect was quoted saying “…the best quality they have seen yet.” The Renaissance Companies also worked with material handling conveyors and racking subcontractors to ensure all permits and inspections were compiled in a timely manner so operations could commence as soon as possible.

Award: Best of NAIOP Industrial Tenant Improvement of the year – 2010